The installation of gas
pipe through the designated wetland areas of Mississippi and Alabama could
prove challenging for any contractor, but the thick-walled pipe specified on
the Gulfstream Project presented new welding challenges for contractor Sunland
Construction Inc. Because the pipe is two times as thick as that typically
used, Sunland relies on innovative welding techniques to decrease the number of
weld passes necessary and most importantly, to assure the welds produced are
consistent, x-ray quality.
Sunland Construction Inc.,
headquartered in Eunice, Louisiana, turned to The Lincoln Electric Company's
Autoweld® automatic orbital pipe welding system for the fill and cap passes and
the STT® (Surface Tension Transfer®) process to lay the critical root pass. By
implementing these new welding technologies, Sunland has been able to remove
one electrode pass from the root pass process as well as eliminate all grinding
from this step. With the Autoweld system, the company has reduced the time to
put in the fill and cap passes.
"We have realized dramatic
improvements since using the new Lincoln welding systems in both higher quality
and time savings," said Joe Ratcliff, Project Manager for Sunland
Construction Inc. "Our welders are proud of the new equipment, it has made
the welding portion of this job run smoothly."
Gulfstream Project
The Gulfstream Project is a natural
gas pipeline that originates near Pascagoula, Mississippi and crosses the Gulf
of Mexico to Manatee County, Florida. Once onshore, the pipeline stretches
across south and central Florida to Palm Beach County. This natural gas
pipeline will serve Florida utilities and power generation facilities,
generating 1.1 billion cubic feet per day of additional natural gas - enough to
supply electricity for 4.5 million homes.
Sunland Construction Inc.'s portion
of the pipeline includes installation of 6.1 miles of 36" diameter pipe in
Jackson County, Mississippi and 9 miles in Mobile County, Alabama.
A 27-year-old company with five
divisions, Sunland won the Gulfstream job through a competitive bid process.
More than 250 employees are being utilized on this project - taking a total of
seven months to complete. Sunland expects its portion of the Gulfstream project
to be wrapped up in early 2002.
According to Ratcliff, preparing
for pipe installation on this job is no small feat. "Before we can even
begin to weld, we must first clear the land, prepare a right of way, install
piling in some areas, erect construction bridges and bring in additional soil
where need. Because of the conditions of the wetland areas, all welding crews
have to work on large, 4 ft. x 20-ft. timber mats. These mats, sometimes put
down in a number of layers, provide a stable, dry work surface. Once work is
complete in an area, Sunland Construction Inc. is also responsible for
restoring the surrounding area to its original condition.
"Welding for this job is
completed with three crews, one welding right after the other," noted
Ratcliff. "The first crew installs the root pass, the second crew
immediately follows using stick welding to accomplish a hot filler pass, and then
the Autoweld crew completes the welding process with fill and cap passes."
Because of the extreme conditions
on the site, the Autoweld process is performed inside of a welding
"house" or modular unit that is lifted and moved every 40 ft. (from
joint to joint) by a Caterpillar Challenger with a side boom.

The Pipe
Pipe for the on-land
portion of the Gulfstream Project is provided by Berg Steel Pipe Corporation of
Panama City, Florida and its parent company, Europipe GmbH of Germany. The X70
pipe ranges in wall thickness from 0.635 to 1.22. This thick-walled pipe was
specified so the pipeline could handle the pressure range of the Gulfstream
system. Pipe is coated with a Fusion Bond Epoxy (FBE) on both the interior and
exterior, and a majority of the pipe is also concrete coated for buoyancy
control.
Root Pass
Sunland Construction Inc. utilized
the STT process because of the advantages it offered.
STT is a modified MIG process that
uses high frequency inverter technology with advanced Waveform Control to
produce high quality welds while also significantly reducing spatter and smoke.
STT technology has the ability to control weld puddle heat independently of
wire feed speed - this allows the welder more control over the puddle and
provides the ability to adjust the heat input to achieve the desired root bead
profile. The welder simply positions the arc on the forward portion of the weld
puddle and follows it around the pipe in a vertical down fashion.

With the system, Sunland welders can achieve a
uniform gap by using an internal, pneumatic clamp to line up and space the pipe
for accurate welding.
For the Gulfstream Project in
particular, STT is able to produce a quality weld and allows an increased
amount of weld metal to be placed on the heavy wall pipe for improved
resistance to cracking. With STT, Sunland only has to make one pass for the
root bead as compared to two passes plus grinding time with stick.
"Since the root pass is the
foundation for the rest of the weld, achieving a high quality, strong and
uniform weld is very important to us," said Ratcliff. "We are very
pleased with the STT. It has allowed us to save time and is an easy system for
our welders to learn. The STT process is very forgiving, meaning that it helps
compensate for misalignments, if and when necessary."
The two STT machines on the
Gulfstream job site are used in conjunction with Lincoln's .045 L-56™ SuperArc®
wire and 100 percent CO2 shielding gas. As compared to blended gases, CO2 is
able to provide better penetration and is less expensive.
"The STT is able to apply a
root bead with great consistency over a wide variety of joint conditions"
explained Ratcliff.
Hot Filler Pass
Once the root pass is complete, the
next team of welders follows closely behind to weld in the hot filler pass. Due
to the thickness of the pipe on this job, Sunland Construction Inc. elected to
put a single downhill hot filler pass over the root with a downhill, low
hydrogen stick process. "The added filler metal we deposited at this stage
gives us additional backing to lay the first wire filler and means that we
don't have to make quite as many passes with the Autoweld system," noted
Ratcliff.
To do this interim step, Sunland is
using Lincoln's LH-D 80 rod with a conventional 300-amp Lincoln belt-driven
welder.
Fill and Cap
For the Gulfstream Project, Sunland
Construction Inc. decided to invest in an automated process to weld the fill
and cap passes. Previously, Sunland has been completing the fill and cap passes
with a 70+ stick electrode, welded vertical down and requiring numerous passes.
"We wanted an automatic method
to increase efficiencies and decrease overall costs," said Ratcliff.
"It was also important for us to find a system that could provide a
quality product but yet was easy to operate.
In its quest, the company contacted
a number of manufacturers to research which system would work best in this
application. "We narrowed down our choices and visited a couple of
manufacturers to try out their systems, one of those being Lincoln Electric,"
noted Ratcliff. "Our team traveled to Lincoln's Cleveland headquarters
where we had the opportunity to run our procedures on an actual Autoweld
set-up. After we returned, we listed the pros and cons of every system and
Lincoln's Autoweld came out on top. A big factor in our decision was the amount
of technical support that Lincoln could provide to us."
The Autoweld system is enclosed in a house, so that welding can be done out of the elements. These houses are moved by sidebooms ( Challengers ) from one length of pipe to the next. Sunland uses six Caterpillar Challengers with PTO driven generators to produce the 100 amps at 460 volts needed to operate the Autoweld and accessories.
Lincoln's Autoweld system uses a
specially designed lightweight-welding head to travel around the circumference
of the pipe. In addition, the unit utilizes an external crawler band placed on
the pipe to one side of the field joint weld bevel. Two machines operating
simultaneously complete the vertical up welding - one machine starts at the bottom
with the other starts on the side. Once the machine that started on the side
reaches the top, it then is positioned to start at the bottom to complete its
side of the pipe. Using the vertical up process is a break from the
traditional, vertical down welding typically utilized for pipe.
Each wall thickness of pipe
requires different machine settings for each specific pass. These settings are
charted and can easily be set from the machine. The Autoweld system uses a flux
core .052" wire and a shielding gas of 25 CO2/75 argon.
With Autoweld, Sunland Construction
Inc. is achieving repetitiously consistent, x-ray quality welds. "Autoweld
makes a very consistent, uniform, and precision-controlled metal deposit,"
noted Ratcliff. "The weld has high tensile strength and good Charpy values
in the weld and pipe heat zones. The machine is also very durable and
dependable."
Sunland's Autoweld system is
powered by an Invertec® V350-PRO, an extremely lightweight inverter that is
able to handle multi-process applications. The hallmark of this power source is
an extremely smooth arc due to the unit's advanced inverter technology.
"We feel the V-350 is the
state of art in welding equipment, it gives you the ability to maintain precise
settings and arc performance," claimed Ratcliff. "Even after long
hours of use on our construction site, the machine was dependable."
Quality Control
All welds once completed are
visually inspected and then x-rayed with an internal crawler. All welds must
meet API 1104 Section 9 requirements.
Service
Sunland Construction Inc. has been
extremely pleased with the service it receives from Lincoln. "The on site
support provided by the Lincoln Electric Mobile team of Troy Gurkin and Steven
Brown has been superb," said Ratcliff. "We also enjoyed tremendous
support from the Cleveland based Autoweld group including Eric Stewart,
Autoweld technician, who was on site for much of the project. Lincoln has gone
out of its way to help us implement our new processes and suggest new
technologies when appropriate."
Sunland has also taken advantage of
Lincoln's training programs on-site and in Cleveland. "Lincoln was
challenged with taking welders at all different levels of expertise and work
with them to learn to understand and operate the Autoweld system. It was a
massive training effort that required quite a bit of Lincoln's time. We
appreciate all they have done to make this job run smoothly."
Future
Sunland Construction Inc. is
already planning on how the new STT and Autoweld machines can be used on future
jobs to increase efficiencies.
Sumber : http://www.lincolnelectric.com/en-us/support/application-stories/Pages/sunland-surface-tension-transfer-welding.aspx
Tidak ada komentar:
Posting Komentar