The hydrotests are conducted mainly to verify the
mechanical strength of pipeline or pipeline sections. Hydrotesting is carried
out by pressurizing the system to a specified internal pressure and holding it
for a certain period of time to check whether or not there is a pressure drop.
If the pressure drops within the hold period, it is assumed that a leak or
leaks may exist somewhere in the system. After the holding period is over, the
pressure is released and a complete visual inspection follows. Standard codes,
such as ASME B31.4, ASME B31.8, and API RP 1110, provide guidance on how to
perform pressure tests of gas and liquid pipelines. Before conducting the tests,
it is necessary to establish the specifications for the test procedures and
equipment. The procedure specifications should include the following:
A description of the pipe sections to be tested (lengths,
elevation, tie-ins, etc.)
·
Test medium (seawater is used for subsea pipelines)
·
Chemicals to be mixed with the test medium (biocide and
corrosion inhibitors)
·
Mixing process of the chemicals with the test medium including
the chemical concentrations
·
Test pressures
·
Test holding time
·
Process of pressurizing
·
Description of all testing equipment
·
Description of testing instrument
·
Monitoring and recording of test pressure
·
Procedure for depressurizing and discharge of test medium
The test pressure is recommended to be set at no less
than 1.25 times the internal design pressure for both hydrostatic testing and
leak testing. The holding time is recommended to be at least 4 hours for
hydrostatic testing and at least 1 hour for leak testing.
A
complete description of the test equipment and instruments is very important
for the success of the tests. The following is a partial list of the devices
needed for the tests:
·
A high-volume pump that can fill the line at high enough
velocity to remove debris and to push the pigs
·
A filter that would remove all particles larger than a certain
size to ensure the test fluid is clean
·
A meter to measure the quantity of water filled
·
Injection pumps for chemical injections
·
A variable speed, positive displacement pump to pressurize the
line. The pump should have a known volume per stroke and should have a stroke
counter
·
A pressure recorder that would continuously record the test
pressure for the whole test period. The pressure measuring equipment should
have an accuracy and repeatability of 0.1%
When planning the hydrotesting and leak testing, a few
issues must be taken into account. The tests should be planned so that
nowhere in the test segment does the pressure level produce hoop stress
near or above the specified minimum yield stress (SMYS). This will require
the test pressure to be determined by taking into full account the effect of
the pipeline profile and external conditions. If the test pressure is
relatively high because of the high design pressure, the pressure relief
valves have to be properly checked and set at the right pressure to
protect the pipeline and the involved personnel. When launching a suite of
pigs from a test-head launcher and receiving into a similar receiver, there is
always concern that not all the launched pigs have been successfully
launched or received into the terminal. It is necessary to install a pig
transmitter device or some kind of remote pig signaling system on the
final pig to confirm the pig launch and reception.
How the
test results will be reported and what will be reported should be defined
before performing the tests. The test records should include the details
of the test operations and details of any failures. The failure report
should include the exact location of each failure the type of failure, the
causes for the failure, and the recommended repair methods. When the tests
are finished, all waste should be disposed of in the correct manner which
should be defined in the company’s waste management and disposal policy.
Sumber : Lee,J.E,2007, Introduction to Offshore Pipelines and Risers.
Sumber : Lee,J.E,2007, Introduction to Offshore Pipelines and Risers.
Palmer,C.A,
2008, Subsea Pipeline Engineering, Usa : Penwell Corporation
Tidak ada komentar:
Posting Komentar